PAC Group | Industrial Electrical Installation

Industrial Electrical Installation

04 Oct 2019

Industrial Electrical Installation Case Study Manufacturing Header Image

PAC Electrical won a tender for the installation of a new sub mains to an existing control panel in a leading industrial factory in the greater Belfast area.

OBJECTIVE

This industrial client required a 200amp 3-phase and neutral supply to be installed to a pre-existing control panel, along with new containment and an earthing system.

PROCESS

PAC Electrical’s design team were able to specify the correct cable type and size, along with a separate earth for the 200amp supply. Once the specification of the install had been designed, our team set to work on the installation, which included the following:

Due to the layout and configuration of the building, the installation of the cable run was challenging, but our team was able to overcome this with their experience and skill-sets coming to the fore.

OUTCOME

PAC Electrical delivered the install of the mains cable with minimum disruption to the client, and all work was carried out under BS7671 with a full set of Risk Assessments and Method Statements (RAMS).

To discuss your specific electrical requirements, talk to one of our team today: we’re here to help, whatever your project.

More Case Studies

PAC Group / Our Clients

Sign up to our newsletter

Keep up-to-date with our latest news, innovations, and projects:

There was a problem with your sign up

You have successfully signed up